“1 Ordering anything from … for any other location of the world – Generally will cause you financial. compliance, & time frame issues.

2 Local Suppliers / Engineers / Clients – generally do not understand International Standards, Laws, Specifications, Other countries requirements. all others should be done with externals Consultants

3 Suggestion – Use Expert Consultants / SME’s (Subject Matter Experts). Suppliers, Clients, EPCs are generally not experts.

4 Accessibility of Equipment for Inspections – Poor access to Lights, slows all processes down. Have Scaffold or EWP available

5 Manpower was too low – Decision was made before Inspection that Technicians were not needed. It was assumed installation was 100% complete

6 Inspector’s findings 100% no issues – Their ‘expertise’ is under-performing

7 Technicians were not trained on this specific Make / Model of Glands

8 Technicians not trained on Barrier Glands

9 Technicians not given specific tools for Glanding

10 Parts and Materials for project were not organized 

11 Receiving Inspection by an Ex Competent Person did not happen for Equipment / Parts / Materials 

12 Manufacturers sent wrong equipment – Buyer did not find this issue

1 Temperature Elements – ATEX, not IECEx

2 Lights – HazLoc (American Only), not IECEx

13 Cable Manufacturer – Cable did not match details of their Datasheets

– Cables were 10.8mm overall Diameter – Datasheet said 12.9mm

– Glands ordered were for 12.5mm to 20mm

– All Glands had to be replaced – Glands at Junction Boxes will be an issue

14 Suggestion – Never order equipment that is close to their design limits

15 Received Incorrect equipment

16 Initial inspection, Testing, Preservation of equipment not done by client

– Bench Testing (Megger, Point-to-Point, Calibration)

– Documentation that came with equipment was not provided for review

– Documentation for Receiving of Equipment not provided

17 Documentation – All documentation not provided for review before site visit

– Equipment to be procured / ordered

– Complete list of ALL Cables

– List of all Individual Equipment, Parts, and Materials

– ITR’s – Inspection Test Reports

– Cable Schedules

18 Documentation – All documentation not provided for review during site visit

– Asked multiple times for documentation to be ready, organized, in Binder

19 Incorrect equipment ordered (ATEX, instead of IECEx) – IECEx was mentioned many times, or ATEX would result in a CAD, which costs more money

20 Belief of Clients approvals, instead of Consultants

21 documentation was disorganized / inefficient to find

22 Technical Queries / Requests for Information were not correctly budgeted.

23 Technical Queries / Requests for Information – Were requested in over +50 emails, Conference Videos, Phone Calls

24 Technical Queries / Requests for Information –  Were not budgeted

25 Technical Queries / Requests for Information – Were never requested via official documentation  

26 Accessibility of Equipment – Maintenance of equipment was not considered

27 Preservation was not well planned for the installation

– No Silicon Grease (DC-4, Molykote) applied to all covers, threads, flamepaths

– Anti-Condensation Packs were not installed

– Cables were poorly secured, where they would swing with the movement of the ship and waves”

This report above – slightly modified from original – I found to be very interesting. It could meet many of Ex projects worldwide. We shall learn from it, and use it as per our own.

Keep up good work!

Arpad

exprofessional.com

veress@exprofessional.com

Leave a Reply

%d bloggers like this: